Earned value in practiceSee where a program really stands.
Explore sample earned value charts, run the core metrics on your own numbers and learn the language of EVM.
See where a program really stands.
Earned value compares the work planned, the work performed and what it actually cost. The charts show a sample program. The calculator lets you run the core EVM metrics on your own numbers.
Cumulative performance
Planned value, earned value and actual cost by month. The gaps between the lines are the story.
Performance indices
Cost (CPI) and schedule (SPI) efficiency against the 1.0 target and a ±10% threshold band.
Variance by control account
Cost and schedule variances that cross thresholds get a written analysis and corrective action.
Sample program data, for illustration only.
EVM calculator
Enter your program's numbers to see its health.
Uses standard EVM formulas: CPI = EV/AC, SPI = EV/PV, EAC = BAC/CPI. A quick check, not a substitute for a full analysis.
The terms behind the numbers.
EV ÷ ACEV ÷ PVBAC ÷ CPIWant this view of your own program?